  "project": "GO3D-WPT-2026-001",
  "issuedOn": "2026-10-29",
  "requestedTarget": "LOD 250",
  "currentAcceptance": "NOT DEMONSTRATED",
  "accuracyStatement": "The current Jambo House interior is an estimated reconstruction from a marked plan and reference photographs. The provisional plan fit is 0.092 m/pixel with a 67 degree rotation; heights and levels are estimated. No registered photo camera network, independently checked dimensions, interior survey control or measured project tolerance has been established. Exterior roof and terrain use 2018-2019 airborne LiDAR and a 2023 aerial texture; wall massing is inferred and current condition is unverified. Model units are metres, but units and detailed appearance do not establish real-world accuracy. Drawings describe this model, not a field-certified as-built. LOD 250 is the requested target and has not yet been demonstrated for acceptance.",
  "reference": {
    "publisher": "VDC Forum / BIMForum Global",
    "url": "https://vdcforum.org/resource-library/bimforum-global-2025-specification-add-lod-250-closing-a-gap-in-bim-for-early-coordination-estimating-and-scan-to-bim/",
    "note": "The reference describes specific quantity and predictable approximate perimeter/interfaces within an agreed tolerance. Its default +/-2 inch example is not adopted as project accuracy or demonstrated here. Confirm reference edition and tolerance in the scope."
  },
  "scopeBasis": "Marc's marked plan: Z01 general flooring/project scope; Z02 bridge flooring above; Z03 lighting only, no flooring. Approximately 18,000 SF is reported, not independently measured. LOD 250 target added by Eddie on 29 October 2026.",
  "items": [
    {
      "id": "A01",
      "item": "Controlling plan, levels and boundaries",
      "state": "Pending confirmation",
      "current": "Marked source and three zone IDs retained; exact venue, building, level, dimensional scale and modeled-scope alignment remain unconfirmed.",
      "remaining": "Confirm venue, floors, current plan revision, actual zone boundaries and whether 18,000 SF includes bridge and lighting areas.",
      "acceptance": "Approved scope/area and level matrix with source revision."
    },
    {
      "id": "A02",
      "item": "Element-level LOD 250 agreement",
      "state": "Requested target",
      "current": "Target recorded; current study is not accepted at LOD 250.",
      "remaining": "Agree required parts and attributes, intended use, reference edition, per-element tolerance, exclusions and reviewer.",
      "acceptance": "Approved element matrix and documented tolerance/check method."
    },
    {
      "id": "A03",
      "item": "Scale, origin, levels and independent checks",
      "state": "Unverified",
      "current": "Metre units; provisional visual plan alignment and estimated floor/height datum.",
      "remaining": "Use reliable dimensioned plans, control or targeted capture to constrain scale/levels and independently check required geometry.",
      "acceptance": "Documented common reference, check dimensions/residuals and accepted tolerance by element."
    },
    {
      "id": "A04",
      "item": "Z01 agreed architectural/floor elements",
      "state": "Partial study",
      "current": "Traced floor footprint, framing, gallery and glazing study objects are represented.",
      "remaining": "Confirm floor limits, openings, wall/column geometry, quantities and required architectural parts. Add only supported missing parts.",
      "acceptance": "Required Z01 elements complete and checked against accepted sources within agreed criteria."
    },
    {
      "id": "A05",
      "item": "Z02 bridge floor and agreed interfaces",
      "state": "Partial study",
      "current": "Bridge deck/guard study present; levels and dimensions estimated.",
      "remaining": "Confirm bridge floor extent, elevation, required edges/interfaces and element quantities; verify geometry.",
      "acceptance": "Required bridge parts and interfaces checked; no concealed support assumptions."
    },
    {
      "id": "A06",
      "item": "Z03 lighting only and reflected ceiling plan",
      "state": "Partial study",
      "current": "Four pendant studies with eight modeled shields each; sloping ceiling/battens and model-derived RCP.",
      "remaining": "Verify actual fixture inventory, identity, positions, suspension/ceiling heights and required properties. Z03 does not add flooring.",
      "acceptance": "Agreed lighting/ceiling elements and RCP correspond; unverified electrical/photometric specs stay unknown."
    },
    {
      "id": "A07",
      "item": "Above-ceiling, structure and MEP extras",
      "state": "Conditional scope",
      "current": "Hidden services are unmodeled; no invented pipes, circuits or concealed rooms.",
      "remaining": "Include only if agreed in Expanded Coordination; obtain usable plans or permitted line-of-sight capture and define required parts/access.",
      "acceptance": "Separate agreed deliverable matrix, source coverage and QC for each extra discipline."
    },
    {
      "id": "A08",
      "item": "Exterior/site scope",
      "state": "Archival / partial",
      "current": "LiDAR-derived roof/terrain and inferred wall massing; no current facade verification.",
      "remaining": "Confirm required exterior coverage/detail and current changes; obtain permitted sources or targeted checks where needed.",
      "acceptance": "Agreed exterior elements with dated source/control and explicit gaps."
    },
    {
      "id": "A09",
      "item": "BIM information and receiving application",
      "state": "Partly checked",
      "current": "335 IFC4 study objects; schema, units and geometry readback checked. Revit handoff and optional local conversion helper supplied; real Revit loading, RVT generation and native-family acceptance remain untested.",
      "remaining": "Confirm receiving Revit version/native format requirements; test linking, categories, levels, names and required property sets.",
      "acceptance": "Receiver-approved model test; native RVT/parametric families only if separately produced and checked."
    },
    {
      "id": "A10",
      "item": "Drawing/model coordination and release",
      "state": "Draft package",
      "current": "11 linked R07 model-derived sheets retain prior model geometry, scales and source hashes; one-page visual review and protected model attachments are available. Delivery remains a study package.",
      "remaining": "Update affected sheets after verified model changes; review dimensions, model consistency, coverage, source hashes and revision log.",
      "acceptance": "Named human QC and owner acceptance against the agreed LOD 250 matrix before release."
    }
  ],
  "workflow": "BIM may start from usable plans and other reliable sources. Scanning checks and revises the baseline where needed. Reuse already captured or sufficiently documented areas when scope changes; add verified detail over time and keep remaining gaps explicit.",
  "measuredProjectToleranceMetres": null,
  "emailsToMarc": "ON HOLD - owner instruction",
  "readinessGuide": "/w/m#scope",
  "revitHandoff": "/review/revit-handoff.html",
  "preScanModeling": "Reconstruct only geometry supported by the agreed controlling drawings, sections, dimensions or other usable evidence. Public photographs support visible interpretation; they do not establish hidden geometry or metric accuracy by themselves."
}